Electrical Tools · Free

Solar 120% Rule — NEC 705.12 Busbar Check

The main breaker and the backfed PV breaker may add up to 120% of the busbar rating — provided the PV breaker sits at the opposite end of the bar from the main. On a 200 A panel with a 200 A main that leaves exactly 40 A, and not one amp more.

Check the busbar

A
0 A200 A

Use the inverter's rated continuous AC output current, from its nameplate — not the array's DC kW. At 240 V, 32 A is roughly a 7.6 kW inverter. The breaker is then sized at 125% of that figure under 690.8(A) and 705.28.

705.12(B)(3)(2) verdict

Fits exactly

PV breaker

40 A

Max inverter

32.0 A

Main + PV

240 A

120% allowance

240 A

Headroom

0 A

See the breakdown
Inverter
PV breaker at 125%
Busbar allowance
Sum of devices
Result
Largest that fits

The PV breaker must land at the opposite end of the busbar from the main.

The method, explained in plain English

# Size the PV breaker — 690.8(A), 705.28
PV breaker = inverter output × 1.25 → next standard rating
# The 705.12(B)(3)(2) test
allowance = busbar × 120%
main + PV breaker ≤ allowance
# The condition that makes it legal
PV breaker at the opposite end of the busbar from the main
+ permanent warning label on the panel

Current enters from both ends

That is the whole justification. With the sources at opposite ends, no section of bar carries the sum — the worst section carries the larger source alone.

Position is not a formality

Put the PV breaker anywhere but the far end and the allowance evaporates, because loads between the two sources no longer split the current.

Breakers, not kilowatts

The rule compares device ratings. Get there from the inverter's continuous AC output at 125% — never from the array's DC nameplate.

A main derate is the cheap fix

200 A down to 175 A opens a 60 A PV breaker. Prove the house never needs 175 A with 220.87 measured demand and it costs one breaker.

Worked examples

The same 200 A panel three ways — and the two amps that decide the job.

1

200 A panel, 7.6 kW inverter — fits exactly

The defaults. 200 A busbar, 200 A main, 32 A of inverter output.

PV breaker: 32 × 1.25 = 40 A
allowance: 200 × 120% = 240 A
sum: 200 + 40 = 240 A
240 ≤ 240 — permitted, with zero headroom

Result: landing exactly on the limit is legal — the code says "shall not exceed", and this equals. This is why 7.6 kW is such a common residential inverter size: it is the largest that drops into a stock 200 A panel with no other work.

2

Same panel, 9.6 kW inverter — fails by ten amps

Nothing changes but the inverter: 40 A of continuous output.

PV breaker: 40 × 1.25 = 50 A
sum: 200 + 50 = 250 A vs 240 A allowance
250 > 240 — not permitted

Result: eight extra amps of inverter cost a breaker size and break the rule. Either accept 7.6 kW, derate the main, or go to a supply-side tap — this is the decision point on most residential retrofits.

3

Main derated to 175 A — 11.5 kW now fits

200 A busbar kept, main breaker swapped to 175 A.

allowance: still 240 A · main now 175 A
room for PV: 240 − 175 = 65 → 60 A breaker
inverter: 60 ÷ 1.25 = 48 A, about 11.5 kW

Result: a $60 breaker bought 50% more solar. Confirm the house genuinely stays under 175 A first — twelve months of utility peak demand at 125% per NEC 220.87 is the accepted way to show it, and most homes are nowhere near.

Maximum solar by panel size

Assuming the main breaker equals the busbar rating, which is the usual case. Inverter kW shown at 240 V single-phase.

Busbar / main 120% allowance Max PV breaker Max inverter ≈ kW at 240 V
100 A 120 A 20 A 16.0 A 3.8 kW
125 A 150 A 25 A 20.0 A 4.8 kW
150 A 180 A 30 A 24.0 A 5.8 kW
200 A 240 A 40 A 32.0 A 7.7 kW
225 A 270 A 45 A 36.0 A 8.6 kW
400 A 480 A 80 A 64.0 A 15.4 kW

Sources & standards: NEC (NFPA 70) 2023 Article 705 — load-side interconnection 705.12, with the busbar options in 705.12(B)(3) and the 120% allowance at 705.12(B)(3)(2); supply-side connection 705.11; power control systems 705.13; circuit current and overcurrent protection 690.8 and 705.28. This tool models the 120% option only — the sum rule, the centre-fed allowance, and the engineering-supervision path in 705.12(B)(3) are separate routes with their own conditions, and one of them may permit an interconnection this check rejects. The opposite-end busbar placement and the permanent warning label are conditions of the allowance, not suggestions. Local amendments, the utility's own interconnection agreement, and the AHJ all have final say.

Frequently asked questions

Common questions about the 120% rule and load-side PV interconnection.

What is the solar 120% rule?

NEC 705.12(B)(3)(2) lets the main overcurrent device and the backfed PV breaker together total up to 120% of the busbar rating, on one condition: the PV breaker must be at the opposite end of the busbar from the main supply. A 200 A busbar with a 200 A main therefore allows 240 A of total supply, leaving exactly 40 A for solar. That 40 A breaker backs a 32 A inverter — roughly 7.6 kW at 240 V.

Why is 120% allowed at all?

Because of where the current goes, not how much of it there is. With the main at one end and the PV at the other, power flows inward from both ends toward the loads in between. No single section of busbar ever carries the arithmetic sum of the two devices — the worst-case section carries the larger of them. The opposite-end placement is not a formality; it is the entire engineering basis of the allowance, which is why 705.12(B)(3)(2) makes it a condition and why the panel needs a permanent label saying so.

How big an inverter can a 200 amp panel take?

With a 200 A main on a 200 A busbar, 32 A of continuous inverter output — about 7.6 kW at 240 V. The arithmetic: 200 × 120% = 240 A allowance, minus the 200 A main leaves 40 A, and a 40 A breaker backs 40 ÷ 1.25 = 32 A of inverter. Going one step up to a 40 A inverter needs a 50 A breaker and lands at 250 A, which fails. Those two amps are the whole difference.

What if the 120% rule doesn't work?

Three routes, roughly in order of cost. Derate the main breaker — dropping a 200 A main to 175 A on a 200 A busbar opens up a 60 A PV breaker, and most houses never come close to 175 A of actual demand. Use a supply-side (line-side) tap under 705.11, which connects ahead of the service disconnect and bypasses the busbar rule entirely. Or fit a smaller inverter. A main derate is usually cheapest, and NEC 220.87 measured demand is how you prove it is safe.

Do I use the inverter's rated output or its breaker size?

Both, in order. The rule compares breaker ratings, so the number that goes into the sum is the PV breaker. But you size that breaker from the inverter's continuous output current at 125% per 690.8(A) and 705.28 — a 32 A inverter needs 32 × 1.25 = 40 A. Using the inverter's nameplate kW without the 125% factor is the most common way this calculation goes wrong.

Does the 120% rule apply to batteries too?

Yes. NEC 2020 rewrote Article 705 to cover all power production sources, and energy storage systems interconnected on the load side face the same busbar arithmetic. A battery inverter that can export is a source. Note that a system able to both charge and discharge may need consideration in both directions, and that 705.13 power control systems are an increasingly common way around a busbar that will not otherwise take the interconnection.

Is the 120% rule the only option in 705.12?

No — and treating it as the only one is why some interconnections get refused unnecessarily. 705.12(B)(3) contains several paths, including the sum rule (all breakers excluding the main not exceeding the busbar rating), a centre-fed panelboard allowance, and a path under engineering supervision. This calculator models the 120% option only, because it is the one nearly every residential job uses. If it fails here, the others are worth reading before reaching for a service upgrade.

Where exactly does the PV breaker have to go?

At the opposite end of the busbar from the input feeder conductor or main breaker. In a typical residential load centre with the main at the top, that means the very bottom pair of spaces. Not near the bottom — the last position. If a full-size breaker already occupies it, that breaker moves. Inspectors check this specifically, and the required warning label spells the rule out for whoever opens the panel next.

Interconnection cleared? Quote the install.

Solar work is equipment-heavy and labour-light, so margin lives in the takeoff. TradesQuote turns a system design into a line-item estimate — modules, racking, conductors, disconnects, labour — validated by a built-in quality control agent.

AI line-item estimates

Quantities, unit prices, and totals generated instantly.

Knowledge base

Upload past jobs so estimates reflect your real pricing.

Shareable & signable

Clients review, accept, and sign from a public link.

No credit card required · 14-day free trial · Cancel anytime

More electrical calculators