TradesQuote

TradesQuote Blog

Copper vs Aluminum Wire: Sizing, Cost, and Where Each Belongs

Copper vs Aluminum Wire: Sizing, Cost, and Where Each Belongs

Aluminum needs 1.59× the circular mils for the same ampacity and reaches 1.64× less far at the same size. Both ratios are constants - which makes the choice a question of scale, not preference.

10 Gauge Wire Amps: Ratings, Breaker Match, and Max Run Length

10 Gauge Wire Amps: Ratings, Breaker Match, and Max Run Length

10 AWG copper is rated 30, 35 and 40 A in the three columns of Table 310.16. You may load it to 30 A - and at 30 A on 120 V it only reaches 48 feet before voltage drop stops you.

Wire Derating Explained: Ambient Temperature and Conductor Bundling

Wire Derating Explained: Ambient Temperature and Conductor Bundling

Six 12 AWG conductors at 40 °C derate to 21.84 A and hold a 20 A breaker. Start from the wrong temperature column and you get 17.60 A - and upsize a circuit that was already legal.

How Many Recessed Lights Do I Need? Count and Spacing by Room

How Many Recessed Lights Do I Need? Count and Spacing by Room

Spacing equals ceiling height ÷ 2, and the wall offset is half of that - which is why a 16 × 12 kitchen lands on a 4 × 3 grid of 12. Plus the light-level cross-check, room-by-room counts, and the code that applies.

What Size Generator Do I Need? Whole-House kW by Load

What Size Generator Do I Need? Whole-House kW by Load

Adding up running watts gets you the wrong answer. A house needing 11.5 kW to run needs 19.2 kW to start its air conditioner - so the set is 20 kW, and a soft starter takes it back to 12 kW.

Electrical Panel Upgrade Cost: 100 A to 200 A

Electrical Panel Upgrade Cost: 100 A to 200 A

What a 100-to-200-amp panel upgrade actually costs, broken down line by line: panel, labor, service conductors, meter, mast, and permit. Plus the five variables that move the number and how much region changes it.

EV Charger Installation Cost: What Drives the $500–$2,500 Range

EV Charger Installation Cost: What Drives the $500–$2,500 Range

A typical Level 2 install runs about $1,300 - $280 of wire, $180 of hardware, $120 of breaker, $150 of permit and $570 of labor. Panel work is the only input that moves it by thousands, and NEC 220.87 is how you avoid it.

What Size Wire and Breaker for an EV Charger?

What Size Wire and Breaker for an EV Charger?

A 48 A charger needs a 60 A breaker on 6 AWG copper - because 625.41 makes EV charging continuous by rule. Plus the two traps: 6/3 Romex is not enough for 60 A, and a 50 A charger costs more than a 48 A one.

Cost to Rewire a House: Per Square Foot by Age and Access

Cost to Rewire a House: Per Square Foot by Age and Access

Whole-house rewiring runs $5–$17 per square foot, and wall access is what decides where you land. A worked 1,800 ft² example, what knob-and-tube and cloth wiring add, and when partial rewiring is the better spend.

Electrical Formulas Cheat Sheet: Ohm's Law to Three-Phase

Electrical Formulas Cheat Sheet: Ohm's Law to Three-Phase

Every formula an electrician actually uses, in the order they get applied - Ohm's law, conversions, ampacity and derating, voltage drop, load calculation, fill, grounding and pricing. With the scope limits most cheat sheets leave out.

Amps to Watts: Conversion With Voltage and Power Factor

Amps to Watts: Conversion With Voltage and Power Factor

Watts = volts × amps × power factor. But amps × volts always gives volt-amperes, and only unity power factor makes them equal - plus why a 20 A breaker is 2,400 W on paper and 1,920 W in practice.

How to Estimate Electrical Jobs: Takeoff, Assemblies, and Labor Units

How to Estimate Electrical Jobs: Takeoff, Assemblies, and Labor Units

The five stages of an electrical estimate - takeoff, assemblies, labor units, overhead, margin - worked on a real job. Plus the markup-versus-margin error that quietly costs contractors 20% of their profit.

Watts to Amps: The Formula for DC, Single-Phase, and Three-Phase

Watts to Amps: The Formula for DC, Single-Phase, and Three-Phase

Amps = watts ÷ volts on DC, ÷ (volts × power factor) on single-phase, ÷ (1.732 × volts × PF) on three-phase. Plus the part that actually matters: why the amps you get are not the breaker size.

Electrician Hourly Rate: Apprentice, Journeyman, Master

Electrician Hourly Rate: Apprentice, Journeyman, Master

Why a $32/hr electrician has to be billed at $105/hr, worked through step by step. The licence tiers, the payroll burden and overhead behind the rate, and why billable utilisation moves it more than anything else.

Ground Wire Size Chart: EGC vs GEC (250.122 and 250.66)

Ground Wire Size Chart: EGC vs GEC (250.122 and 250.66)

Two different conductors get called the ground wire. The EGC comes from Table 250.122 by breaker rating; the GEC comes from Table 250.66 by service conductor size, then gets capped by which electrode it lands on.

GFCI vs AFCI: What Each Protects and Where the NEC Requires It

GFCI vs AFCI: What Each Protects and Where the NEC Requires It

GFCI detects current leaking out of a circuit and protects people; AFCI detects arcing and protects property. Which the NEC requires in each area of a dwelling, why kitchens need both, and how to diagnose nuisance trips.

Conduit Fill Chart: How Many Wires Fit in EMT, PVC, and RMC

Conduit Fill Chart: How Many Wires Fit in EMT, PVC, and RMC

Maximum THHN conductors for every common trade size of EMT, PVC, and RMC, plus the Chapter 9 Table 1 fill limits, the 60% nipple allowance, and why bundling derating usually limits you before fill does.

How to Calculate Conduit Fill (NEC Chapter 9, Tables 1, 4, and 5)

How to Calculate Conduit Fill (NEC Chapter 9, Tables 1, 4, and 5)

The Chapter 9 area method in four steps, worked on mixed conductor sizes where Annex C can't help. Includes the 60% nipple allowance and the Note 7 rounding rule that explains why Annex C sometimes reads one conductor higher.

Box Fill Calculation: Counting Conductors per NEC 314.16

Box Fill Calculation: Counting Conductors per NEC 314.16

How to calculate box fill: the Table 314.16(B) volume allowances, what counts as one, what counts as two, what counts as nothing, and a worked single-gang example that lands on 18.00 cubic inches.

Residential Load Calculation: NEC 220.82 Step by Step

Residential Load Calculation: NEC 220.82 Step by Step

Both legal methods worked on the same house: the 220.82 optional calculation and the standard Part III method with its per-category demand factors. Why a 12 kW range counts as 8 kW, and why the two methods land 21 amps apart.